Silicon Box starts basic design of its Italian chiplet packaging plant

At Novara, the company is designing the cleanrooms and utilities around a panel packaging process it already runs in Singapore.
A technician working in the Jefferson Lab cleanroom.

Silicon Box has begun basic design of its planned €3.2bn assembly and test plant in Novara, where it intends to reproduce the panel packaging process already running at its Singapore operation. The Italian facility would be its first manufacturing site outside Singapore, assembling chiplets from different manufacturers into finished packages and testing the resulting devices.

The design work brings that production process into the plans for the buildings and their services. Stantec is coordinating the project, external infrastructure and utility connections as well as handling permitting, while Drees & Sommer is designing the production and utility buildings, cleanrooms and equipment interfaces. Both firms were appointed in 2025, with construction currently expected to begin in 2027.

For the plant designers, Singapore provides an operating reference for the relationship between the packaging equipment, cleanroom layout and utilities. Chief operating officer Jae Hak Yee describes that operation as having demonstrated high volume production and high yield, although Silicon Box has not released numerical yield data. The company intends to carry its experience there into Novara before construction begins.

Within the packaging line, dies with different functions and dimensions have to be connected electrically and incorporated into a mechanically sound assembly that can be tested as a finished component. The interconnect layout and test flow are therefore part of the process being accommodated by the new facility, alongside the material movements and services that keep the equipment running. Novara’s role is assembly and test, taking dies through those stages after fabrication.

Silicon Box and the Italian authorities presented the development, known as the Vulcan project, in Novara on 9 November. They expect it to create 1,600 direct jobs on a site covering 60 hectares, with space for later expansion as equipment and production needs change.

The utility plans include water reuse, recovery of process heat and photovoltaic generation. Those features remain subject to design development and regulatory requirements, while the company has yet to set a date for customer production.

Sources: Silicon Box design milestone; Joint announcement of the Novara project; Stantec’s appointment and design remit.

Continue reading