When does the clock start on a custom RF amplifier?

SV1AFN quotes a typical four to five weeks to build and deliver its configurable RF power amplifier, depending on the specification and its workload. The range spans 45 MHz to 5.85 GHz across different variants, with output options of 10 W, 30 W, 50 W and 100 W on a 28 V DC supply. The date for a 30 W build over one band does not automatically cover a higher-power build over another, so tie the date to the configuration being quoted.
Set the test conditions before the date
Give the supplier the band edges, output level and conditions under which the amplifier must meet its limits. For example, an output quoted at the centre frequency and measured in a short burst does not establish that the amplifier will deliver the same power at the edge of the band in continuous operation. Put the required operating mode in the request and ask which parts of the specification the supplier will demonstrate on the finished unit.
An amplifier assembled from catalogue options may go straight into production; a change to a connector or mounting face could first need a drawing, approval and a sample. Find out which steps apply before relying on the estimate. In particular, ask whether the factory can start the balance while the first unit is being assessed.
| Put this in the quote request | What it settles |
|---|---|
| A configuration or part number, with frequency band and output conditions | Which build the estimate applies to. |
| The event that starts the clock, including any drawing or sample approval | Whether the quoted period covers the work before the factory releases the build. |
| Test limits, the acceptance record and the number of units it covers | Which checks are done at the supplier and which are still needed on receipt. |
| A committed ship or delivery date, with quantities for any split shipment | When each batch reaches the project. |
A week for drawing approval followed by five weeks from approval puts delivery six weeks after the order was placed. That is an illustrative schedule. Putting the agreed date, configuration and acceptance conditions on the purchase order gives both parties a reference if the specification changes.